Improve Your Job Security with Weekly CAD Management Reports

happy No comment

Improve Your Job Security with Weekly CAD Management Reports

September 26, 2012 By: Robert Green


If your senior management team does not understand the extent of what you do, they'll undervalue you. Keep them fully informed with concise summaries of your activities.

Over the past several weeks, I've been traveling to speak with many groups of CAD managers, and one concern That has come up Repeatedly is job security. One of the Best Ways to Ensure That upper management values ​​your position is to keep them informed about what you DO. I've been very surprised by how many CAD managers do not report to Their senior management team on a regular basis - at omission That puts Their careers at risk!

In this edition of the CAD Manager's Newsletter, I'll make the case did reporting is a task You Should Embrace - it's critical to your success. And do not worry, I'll give you some tips to make reporting quick and easy.

Why You Need to Speak Up

Because you are the only CAD manager in your department or company (and most senior management staffs do not understand what you do), there's nobody else who can report on your CAD management tasks. So you only have two choices: You can report Either what you do to your management team, or you can allow them to remain in the dark about your work.

If you fail to inform your management team about your activities, many problems can result. Here are a few:

  • They want to believe CAD management is easy. People who do not understand the details of what you do will almost always underestimate how hard your job is. And When users or managers think your job is easy, they'll try to load even more tasks Onto you - thereby reducing your effectiveness.
  • They will think CAD management is limited to software. If your management team thinks CAD management is just about software, they 're overlooking the many training, support, and standards issues CAD managers deal with. And that Means They Will not give you the support you need to handle Those non-software issues.
  • They want to be blind to danger on the horizon. Let's say your company has long put off replacing an old, cranky plotter. If you keep quiet about the risk of a plotting disaster, you'll not only preside over the Resulting chaos, so you'll take some of the blame: Management will ask why you never informed anyone.
  • They will think CAD management is all overhead. When your senior management team equates with CAD management overhead, They start to question Whether your position is even needed. And When That happens, your job is anything but secure.

If allowed to persist, will combine to create impressions thesis a negative impression about CAD management in general, and you in particular.

Improve Your Job Security with Weekly CAD Management Reports
Reporting Is the Answer

So how do you get management to better understand your situation and value you more highly? You tell them what you do, via reports did are targeted for executive management to audience! These targeted reports include the Following:

  • History. Communicate what you've done via a task log.
  • Forecasts. Communicate what you're planning to do via objectives.
  • Project support. Outline how much you do to make sure projects go out correctly and on time.

The key characteristics of synthesis reports are clarity and brevity. Senior managers are always in a hurry, and They Do not want to muddle through anything lengthy or wordy.

Your goal in each report is to paint a clear picture of what being the CAD manager is all about. By detailing all the tasks you complete, you take on responsibilities, objectives you have for Improving the Company, and resources you need, you'll be viewed as "in charge" and "more managerial" - qualities thatwill resonate with your senior management staff.

A Simple Reporting Format

The reporting format that works best for me uses a task diary with prioritized objectives delivered on a weekly basis. This report compiles what you've already done and what you hope to do in a single-page, easy-to-read report. Here's a quick example:

This week I:

  • Installed a new plotter on the Third Floor (4 hrs)
  • Held job kickoff training for Project X (3 hrs)
  • Edited plotting standards for Project Y (1 hr)
  • Provided tech support for Project Z (3 hrs)
  • Peformed Production Engineering (32 hrs)

Total: 43 hrs

Next week I plan to:

  • Hold a plotter training session for Project Y (3 hrs)
  • Document / test new Revit families (5 hrs)
  • Provide Technical Support for Projects Y & Z (? Hrs)
  • Perform Production Engineering (32 hrs)

I've created a very simple spreadsheet, titled "CAD Manager Report," that you can download and use as a starting point for your own reports if you wish.

The Benefits of a Weekly Report

I've always chosen to deliver reports on Mondays or Fridays, but the best day of the week to deliver your reports is the day your boss is most likely to be in the office and have enough time to read it.

The advantages to submitting a report using my suggested format are many, but the primary ones for you are:

  • Recording your achievements. Your task diary builds a chronological list of the various tasks you perform, and documents the exceptional range of tasks you work on.
  • Building Value. Once your management understands how many diverse projects you tackle, theywill begin to understand your value (particularly When They see how much you get done in CAD ​​management the little time left after you complete your design duties).
  • Blowing your own horn. You raise the awareness of what CAD management really is and how valuable it is by simply listing your tasks for management to read about. In a sense, you can brag about yourself without seeming to do that.
  • Keeping yourself on task. You get the benefit of a review of what you've Actually Achieved each week, Which keeps you focused on what you're trying to accomplish. This sort of mental discipline is hard to maintain When fighting the frequent, distracting Fires of CAD management, but a written weekly report will help keep you on track.

Of course, your management team so benefits from timely reporting, Because They keep up with your tasks, challenges, and abilities. So They start to understand what management can do to CAD help get projects completed more Quickly and less expensively!

Slay the overhead Myth

You'll note in my suggested reporting format did I document not only the CAD management tasks, but all tasks in a Given Week. My primary reason for taking this approach is to show That CAD management is only part of what most CAD managers do, and did the tasks are not Merely overhead. I've come to accept the fact constant battle over CAD management Being an overhead activity will always be with us, so we might as well tackle it head-on in our reports.

To battle the perception of CAD management as overhead, I've done in my sample the Following Report Format:

  • Reference projects. Wherever possible, I draw connections between CAD ​​management tasks and specific projects to demonstrate management value.
  • Validate training. I also tie kickoff training to a Particular Project.
  • Show the value of tech support. By highlighting the projects for Which I Provide tech support, the support task Becomes valuable to the project.

In all cases, I did stress projects would not get done nearly as well as almost or without CAD management coordination. And, obviously, if CAD management is Performed on behalf of actual projects, it Should not be classified as general overhead!

Summing Up

I'm aware thatmany of you may be thinking, "I've got enough to do without having to create a weekly report!" But if you are not communicating what you do and how crucial CAD management is to upper management, your job will not be as secure. Truly, you can not afford not to spend a few minutes on thesis reports.

I'd recommend you take advantage of the fact report template I've provided, and create your own weekly CAD management report. I'm positive When I say it'll be the best 15 minutes you invest in your career every week.